Total Area
606m² wHOLE.Protect SOLID™
45,200m² ComFlor 51+
6,900m Edge Trim
26,625m² of Safety Netting
93,600no. Shear Studs
-
Main Contractor
Wates Construction Ltd
-
Steel Contractor
Cahill Welding Services Ltd
-
Budget
£1.5 million
Composite Profiles are contributing to the expansion of Britain’s high-tech society building Data Centres across the UK. Two projects in Slough firmly put Composite Profiles on the map as the go-to, solutions-led metal decking contractor in the UK’s Advanced Technologies sector.
The Slough Data Centres project consisted of two schemes – a 18,600m², 3-storey block, closely followed by a neighbouring 26,600m², 3-storey block, each with floor heights 5.5m to 6.5m. Each project was secured following early engagement at tender stage, and 3 months of meticulous planning of the method, sequence and access requirements of safety netting to enable the installation of the decking on the third floor first. During the early engagement period, Composite Profiles also identified an opportunity to enhance safety protection by adding 606m² of wHOLE.Protect GRP void protection system, followed by phased edge protection and shear-stud welding, once the safety netting had been removed.
Both projects separately led to Highly Commended status by FASET at the Excellence of Work Awards, 2021 & 2022.
By nature, a Data Centre needs to securely house rows and rows of valuable and heavy technology, which requires to be secured and protected from conception. The overriding priority and challenge facing the Composite Profiles team was how to safely and securely build top-down, commencing with the third-storey decking, which was required first to house the major plant.
The client’s focus was to handover the plant rooms (top floor areas) as soon as possible to allow the following contractors to start in these areas as the building progressed below. The client’s programme detailed a sequence of Level 3 first, followed by Level 1, finishing with Level 2; with rope access safety netting installed to Levels 3 and 2, and MEWP access to Level 1. Composite Profiles were subsequently enlisted to help plan the build sequence and coordinate with the steel erectors and scaffolders.
The second biggest challenge was that the end client required a system to fully cover 606m² of service voids with a product that could be adapted to suit services as required.
After reviewing the client’s original planned build sequence, Composite Profiles proposed a change to the sequence.
The solution proposed was to erect the safety netting to Level 2 via MEWPs closely followed by Level 1 and Level 3 in tandem, once the metal decking had been installed to Level 2. Level 3 being rope access, and Level 1 access via MEWPs. With the MEWPs operating through the first floor steelwork, without early engagement, this can cause a problem where they clash with the placements of the metal decking packs. By collaborating early with Composite Profiles, the team were able to mitigate this by detailing the decking packs to be landed over the beams, maximising the amount of clear open space for the MEWPs to operate. This enabled continuity of programme works for the Safety Netting and Decking Installation Teams, who demonstrated streamline precision to complete phases ahead of programme. This innovative sequence shaved weeks off the client’s original programme, reduced rope access requirements and an overall reduction in site preliminaries, which saved the client significant costs.
By supplying and installing Composite Profiles own edge protection, the team were able to phase the works to complete 50% of each block, as the steel erection was completed. This streamlined approach ensures continuous installation and handover of each block, as early as possible.
Composite Profiles solution for the 606m² of service voids was the design and installation of their GRP void protection system, wHOLE.Protect SOLID™, which they adapted on-site, hole-by-hole to fit requirements.
“During construction, we went back to the boardroom with Wates to work collectively on proposals that would assist them in securing future projects. Working collaboratively and offering solutions from bottom-up helped put Wates Construction in pole position to secure a string of projects on Europe’s largest trading estate in single ownership.”
Joel Nurser, Managing Director, Composite Profiles